MonteCarloProject allows to set different dependency types between predecessors and successors.
Dependencies are set in the task display and they are always described from predecessor to successor. There are following dependency types (see picture 1):
- Finish-to-start. Successor can be started when the predecessor is finished.
- Start-to-start. Successor can be started when the predecessor is started.
- Finish-to-finish. Successor can be finished when the predecessor is finished.
- Start-to-finish. Successor can be finished when the predecessor is started.

Picture 1. Task display and dependencies.